Agenda item

Agenda item

Crematorium Matters

Report by the Crematorium Manager (attached)

Minutes:

The Joint Committee considered a report by the Crematorium Manager (previously circulated).

 

i)          Staffing Update

 

That a part-time gardener had retired after 20 years’ service and that in line with the service improvement plan and reduced post-autumn workload the recruitment would take place in the spring probably by an apprentice/hybrid appointment.

 

ii)         Crematorium Figures- (excluding NVF)

 

The Cremation figures were noted. The Crematorium Manager reported that there had been 132 cremations in October of which 30 had been direct cremations. The total number of direct cremations to date were 176.

 

iii)        Metals Recycling Charity Award

 

It was noted:

 

That Cruse had been awarded £11,600

 

Rota for subsequent awards:

 

Children’s Hospice SW

Families in Grief

North Devon Hospice

Cruse

 

iv)        Service Improvement Plan

 

It was noted that a survey had been circulated to Funeral Directors seeking their views on the current service delivery and ideas for improvements. A copy of the questions and the results were tabled.

 

It was hoped that this would also help inform any decision making around pricing at the next Joint Committee meeting. Information regarding the National and South West crematoria statistics were tabled.

 

A question was raised regarding the apparent lack of awareness of Memorial only Services provided at the Crematorium.

 

v)         Crematorium Solar Panels

 

It was noted that due to technical issues with Brynsworthy it had been

agreed that the Crematorium progress as a stand-alone solar panela project. A preliminary single quote had been obtained based on current electricity costs which, whilst it incorporated some incorrect presumptions (such as use of the copper roof), did give an insight into costs and time to break even. The estimated cost for a basic 70KW system (no storage) was £61,500 with an annual electricity bill saving of £6,687, a payback period of 7 years 4 months and net savings over 20-years of £207,116.

 

It was noted that the funds for the project could be met from the Budget

Management reserve.

 

It was also suggested that grants may be available for the project.

 

It was agreed that the Crematorium Manager be authorised to seek tenders for the provision of solar panels.

 

vi)        Projects

 

It was noted that a 2.5 day closure for cremator servicing would start on 4th November. It had previously not been required to close for 6-monthly servicing but enhanced safety protocols imposed by the service company had made this necessary. A number of projects had been timed to use this opportunity.

 

Peace Garden: The works would be starting 4th November to create a peaceful garden with seating, water feature and pergola on the old garage site. The noisy elements would be largely completed at this time. Funding source was from a S106 payment. Completion of ground works was likely in late December/early January.

 

The tarmac repairs and the hearse bay marking would be completed at the entrance.

 

Drainage works: The ramp from the upper car-park by the Rowan Chapel frequently had an overflow of water when it rained. Drains were being installed to mitigate this flow of water where vehicles and visitors passed.

 

Installation of a replacement gas meter.

 

vii)       Cremator Maintenance

 

It was noted that a number of costly repairs had already been carried out this financial period. It was anticipated that some additional expensive works would be required in the next few months: Flue perforation at base (fortunately the ‘cold-side’) (quote received of £33,000), damper on one cremator and hearth replacement (approx. £33,000). These works may require funding through the equipment reserve as anticipated for non-routine maintenance.

 

It was noted that these costs would be met from the Equipment Replacement reserve.

 

viii)      Christmas Arrangements

 

It was noted that the Crematorium would be closed from 24th December 2024 and re-open on 2nd January 2025

 

Supporting documents: