10 Year Capital Strategy 2021-2031

Meeting: 24/02/2021 - Council (Item 214)

214 10 Year Capital Strategy 2021-2031 pdf icon PDF 535 KB

(NOTE: A copy of the report that was considered by the Strategy and Resources Committee held on 1 February 2021 is attached).

Minutes:

Council received a presentation by the Head of Resources regarding the 10 Year Capital Strategy 2021-2031 (circulated previously).

 

The Head of Resources highlighted the following:

 

·         The Capital Strategy was reviewed annually by Full Council prior to each financial year.  The Strategy set out the ‘governance arrangements’ for capital projects coming forwards as detailed in section 4.3.

·         All capital projects required a business case, reviewing options, risks and associated costs.  Project Appraisal Group (PAG) comprised of the; Chief Executive, Business Information Systems Manager, Head of Resources and Accountancy Manager who would then meet to score the proposed project.

·         In addition to the original approval of the project, a separate approval would also be sought from the Committee and then Full Council to release the capital funds three to six months before the project was due to start. 

·         Medium Term (2021-2025) as set out in the table in paragraph 4.4 set out the impact of capital financing need, impact this had on the annual borrowing cost and then the overall Medium Term Financial Strategy budget gap, including the additional borrowing.

·         For 2022/23 current projections showed a medium term financial strategy budget gap of £2.3m increasing to £2.9m in 2024/25.

·         The Council would look to become more entrepreneurial in how it delivered services to generate extra income and reduce costs in line with the commercialisation strategy. The Council would also have to review a number of options for bridging the budget gap and any such financial benefits these may produce; these would be subject to further reports being presented to Members. 

·         The estimated Capital Financing Requirement (CFR) for March 2021 was £5.76m which increased to its peak in March 2025 at £18.79m. The capital financing figures would increase further by up to £4.4m in light of the funding for the Future High Street Fund project approved by Council on 17 February 2021. This substantial increase in CFR reflected the £38m capital programme over the medium term including the new Leisure Centre. 

·         The Council would receive an annual management fee in relation to the running of the new Leisure Centre to help offset an element of the borrowing costs.   

·         Longer Term (2025-2031) as set in the table in paragraph 4.5.  The Council had identified two main areas of capital expenditure within the long term forecast which are necessary to maintain business as normal i.e. the vehicle replacement programme, as the works and recycling fleet have an eight year life cycle; and the on-going maintenance of our ICT infrastructure.  Projected investment was required in these two areas.  The longer term model then builds this investment into the spend plans and extends the Medium Term Financial Strategy position up until 2031.  The CFR was generally on a downward trend from £17.17m in 2025/26 to £14.28m by 2030/31. External borrowing over the longer term remained at a high level, £12m and above, again assuming the under-borrowed position remained prudent and sustainable.

·         As a result of the high borrowing, the annual borrowing cost would continue to  ...  view the full minutes text for item 214


Meeting: 01/02/2021 - Strategy and Resources Committee (Item 255)

255 10 Year Capital Strategy 2021 to 2031 pdf icon PDF 535 KB

Report by Chief Financial Officer (attached)

Minutes:

The Committee considered a report by the Chief Financial Officer (circulated previously) regarding the 10 Year Capital Strategy for 2021 to 2031.

 

The Head of Resources highlighted the following:

 

·         The Capital Strategy was reviewed annually by Full Council prior to each financial year.  The Strategy set out the ‘governance arrangements’ for capital projects coming forwards as detailed in section 4.3.

·         All capital projects required a business case, reviewing options, risks and associated costs.  Project Appraisal Group (PAG) comprised of the; Chief Executive, Business Information Systems Manager, Head of Resources and Accountancy Manager who would then meet to score the proposed project.

·         In addition to the original approval of the project, a separate approval would also be sought from the Committee and then Full Council to release the capital funds three to six months before the project was due to start.

·         Medium Term (2021-2025) as set out in the table in paragraph 4.4 set out the impact of capital financing need, impact this had on the annual borrowing cost and then the overall Medium Term Financial Strategy budget gap, including the additional borrowing.

·         For 2022/23 current projections showed a medium term financial strategy budget gap of £2.3m increasing to £2.9m in 2024/25.

·         The Council would look to become more entrepreneurial in how it delivered services to generate extra income and reduce costs in line with the commercialisation strategy. The Council would also have to review a number of options for bridging the budget gap and any such financial benefits these may produce; these would be subject to further reports being presented to Members.

·         The estimated Capital Financing Requirement (CFR) for March 2021 was £5.76m which increased to its peak in March 2025 at £18.79m. This substantial increase in CFR reflected the £38m capital programme over the medium term including the new Leisure Centre.

·         The Council would receive an annual management fee in relation to the running of the new Leisure Centre to help offset an element of the borrowing costs.  

·         Longer Term (2025-2031) as set in the table in paragraph 4.5.  The Council had identified two main areas of capital expenditure within the long term forecast which are necessary to maintain business as normal i.e. the vehicle replacement programme, as the works and recycling fleet have an eight year life cycle; and the on-going maintenance of our ICT infrastructure.  Projected investment was required in these two areas.  The longer term model then builds this investment into the spend plans and extends the Medium Term Financial Strategy position up until 2031.  The CFR was generally on a downward trend from £17.17m in 2025/26 to £14.28m by 2030/31. External borrowing over the longer term remained at a high level, £12m and above, again assuming the under-borrowed position remained prudent and sustainable.

·         As a result of the high borrowing, the annual borrowing cost would continue to put pressure on the Council’s revenue budget each year. The projected cost of borrowing was £1.57m in 2025/26 increasing to £1.64m in 2030/31. 

·         For 2025/26 current  ...  view the full minutes text for item 255