Meeting: 04/11/2022 - Joint Planning Policy Committee (Item 31)

31 Local Plan Review pdf icon PDF 920 KB

To consider the report by the Senior Planning Policy Officers (attached)

Additional documents:

Minutes:

The Committee considered the Local Plan Review Report by the Senior Planning Policy Officers (NDC & TDC) (circulated previously).

 

The Senior Planning Policy Officer (TDC) addressed the Committee and outlined the report. He highlighted the following:

 

·         Extensive work had been undertaken to prepare draft responses in the PAS Assessment toolkits, with work ongoing to finalise the assessments.

·         At the end of 2020 it had been agreed by the two Councils that the NDTLP would be reviewed and updated on a comprehensive basis, without which the current plan could potentially be out of date by the end of October 2023.

·         The agreed approach had regard to: a series of external pressures; a reconsideration of local priorities; and an opportunity to address policy gaps.

  • it was considered prudent to consider whether a comprehensive update remained the most appropriate course of action, recognising:
    • the Local government financial context
    • uncertainties relating to the national planning context, in particular the planning reform agenda and
    • potentially altered member aspirations
  • The PAS provided a Toolkit to guide authorities through the process of reviewing and updating a local plan, whether a partial or full update.
  • Draft PAS Toolkits were completed and provided as appendices to the report:

o   Appendix (a) Local Plan Review Assessment: Opportunity to consider how well the plan is performing and if remains effective

o   Appendix (b) Local Plan Form and Content Checklist: Opportunity to consider whether the provisions of the plan conform to national policy.

·         The draft findings were that the Local Plan:

o   Remained broadly effective in shaping and delivering development

o   Was generally achieving the delivery of affordable housing and infrastructure associated to growth

o   Was on-the-whole contributing to the delivery of economic development on allocated sites.

·         There were recognised areas of silence or non-compliance, which had generally resulted from changes to national planning policy, these included: 

o   Approach to Town Centres

o   Demonstrating a 5-year housing land supply

o   Approach to calculating housing requirement

o   Coastal Change Management Areas

o   Accommodation for Travelling Communities

o   Biodiversity Net Gain

·         The draft conclusion, provided through the PAS Toolkit Assessments was  most Local Plan provisions remain fit for purpose and are broadly in conformity the national planning policy with the significant exception of a five-year housing land supply

·         In reviewing approaches for taking the Local Plan forward three broad options were suggested

o   1) Comprehensive Update

o   2) Partial Update / Plan Supplement or

o   3) Slow down, pause or do nothing for now.

·         Each approach had ‘pros and cons’ but it was noted that a comprehensive update did not mean that the effective parts of the existing plan would be disregarded. It was possible that a supplement could be considered to ‘fill gaps’ in the plan.

·         A comprehensive update would need to be based on updated evidence with new plan period and a five-year housing supply would need to be demonstrated at the point of adoption.

·         Most site remained deliverable but it would need to be considered whether those sites were still the ‘right  ...  view the full minutes text for item 31