We are seeking a structural engineer to
complete the required design and check work for 37 Boutport Street
to comply with the scope of the original Clarke Bond instruction
and following Clarke Bond ceasing trading. It will include the
following: C&S due diligence (DD) check, RIBA Stage 5 and 6
remaining works, Building Control pack if required, Check and
re-badging of the CB construction drawings (to become Curtins
drawings).
Reasons for the decision:
On the 20th December we received news (without
warning) that Clarke Bond, the Structural and Civil engineer for
the FHSF project had ceased trading with immediate effect. This
leaves the Boutport Street project without structural engineer
support. This is a complex project, which includes a detailed steel
construction that requires engineer sign off. A contractor is
working on the site and any delay caused by a lack of structural
engineer would have client culpability and incur a fee –
given the scale of this project the weekly prelim costs are
significant. NDC reached out to Curtins as the structural engineer
who had been leading the work on Boutport Street had recently left
Clarke Bond and moved to Curtins. She has detailed knowledge of the
project. Having just joined the firm she has capacity and could
start work on the project immediately. Using Curtins is considered
best value for the Council as they know the project in significant
detail (any other engineer would take significant time to get up to
speed) and can start immediately reducing any ongoing delay that an
open procurement route would incur.
Publication date: 10/01/2025
Date of decision: 10/01/2025
Accompanying Documents:
- Engineer for Future High Street project PDF 374 KB
- Engineer for Future High Street project